LIST OF JOBS EXECUTED - ONLINE LEAK REPAIRS

S/N JOBS EXECUTED CLIENT DATE
1 ON-LINE PIPELINE LEAK REPAIR ON 14" GAS PIPELINE - AFAM NIGERIAN GAS COMPANY MAY 2007
2 ON-LINE PIPELINE LEAK REPAIR ON 30" GAS PIPELINE - EFFUNRUN UGHELLI NIGERIAN GAS COMPANY AUGUST 2007
3 ON-LINE PIPELINE LEAK REPAIR ON 24" GAS PIPELINE - IKOT NIGERIAN GAS COMPANY OCTOBER 2007
4 ON-LINE PIPELINE LEAK REPAIR ON 24" GAS PIPELINE - AJAOKUTA NIGERIAN GAS COMPANY OCTOBER 2007
5 ON-LINE PIPELINE LEAK REPAIR ON 24" GAS PIPELINE - IYANG NIGERIAN GAS COMPANY NOVEMBER 2007
6 ON-LINE PIPELINE LEAK REPAIR ON 14" GAS PIPELINE - AFAM PIPELINE NIGERIAN GAS COMPANY NOVEMBER 2007
7 ON-LINE PIPELINE LEAK REPAIR ON 36" PIPELINE GAS AT KP 144 NIGERIAN GAS COMPANY NOVEMBER 2007
8 ON-LINE PIPELINE LEAK REPAIR ON 2" STATION PIPELINE - UGBOKODO NIGERIAN GAS COMPANY DECEMBER 2007
9 ON-LINE PIPELINE LEAK REPAIR ON 36" GAS PIPELINE - KP 159 NIGERIAN GAS COMPANY JANUARY 2008
10 ON-LINE LEAK SEALING OF VANDALISED 14" GAS PIPELINE AT OBIGBO NORTH NIGERIAN GAS COMPANY JANUARY 2008
11 ON-LINE PIPELINE LEAK REPAIR ON 16" UGHELLI-ALADJA GAS PIPELINE NIGERIAN GAS COMPANY FEBRUARY 2008
12 ON-LINE PIPELINE LEAK REPAIR ON 30" GAS PIPELINE - OWHORDE-UBEJI NIGERIAN GAS COMPANY FEBRUARY 2008
13 ON-LINE PIPELINE LEAK REPAIR ON 24" GAS PIPELINE - OGAN/UGBEDU NIGERIAN GAS COMPANY FEBRUARY 2008
14 GAS SUPPLY TO GUINNESS BREWERY, BENIN - THRUSTBORING - PIPE CASING CLAIM IESL/BOAB MARCH 2008
15 ON-LINE LEAK REPAIR OF 2NOS - 21/2" COOLING WATER PIPELINE NOTORE CHEMICAL APRIL 2008
16 ON-LINE LEAK REPAIR ON ELP-C OGHARA SWAMP PIPELINE NIGERIAN GAS COMPANY MAY 2008
17 ON-LINE 24" PIPELINE REPAIR AT KP 42 SAPELE NIGERIAN GAS COMPANY JUNE 2008
18 ON-LINE REPAIR OF VALVE LEAK AT ELEME PETROCHEMICAL INDORAMA ELEME PETROCHEMICAL JULY 2008
19 ON-LINE LEAK REPAIR OF INTERNAL PIPINGS AT NOTORE NOTORE AUGUST 2008
20 ON-LINE LEAK REPAIR OF VANDALISED 30" - WGTP & 16" - ALADJA ERIEM GAS PIPELINE NIGERIAN GAS COMPANY SEPTEMBER 2008
21 ON-LINE LEAK REPAIR VANDALISED GAS PIPELINE REPAIR AT OBUHIA ASA AT KM-21 ABA NIGERIAN GAS COMPANY DECEMBER 2008
22 ON-LINE REPAIR OF VANDALISED 24" EXCRAV - LAGOS PIPELINE AT UGBOKODO NIGERIAN GAS COMPANY JANUARY 2009
23 PATCH WELDING ON PIPELINE OBIGBO, POINT A, B & C NIGERIAN GAS COMPANY FEBRUARY 2009
24 PATCHING ELEMENT OF -14" AFAM PIPELINE NIGERIAN GAS COMPANY FEBRUARY 2009
25 ON-LINE PIPELINE REPAIR AT NGC HEAD OFFICE, WARRI NIGERIAN GAS COMPANY MARCH 2009
26 ON-LINE PIPELINE LEAK REPAIR ON 30" GAS PIPELINE - OWHORDE-UBEJI NIGERIAN GAS COMPANY MARCH 2009
27 ON-LINE 14" PIPELINE REPAIR - BERGER IN LAGOS XAPON/NGC APRIL 2009
28 ON-LINE 16" LEAK REPAIR - AJAOKUTA XAPON/NGC MAY 2009
29 ON-LINE LEAK REPAIR FLANGE AT AGIP GAS PLANT KWALE KUMBI SALEH/AGIP JUNE 2009
30 PATCHING WELDING PIPELINE AT KM 147 NIGERIAN GAS COMPANY JULY 2009
31 ON-LINE 30" GAS PIPELINE REPAIR AT USI - EFFURUN NIGERIAN GAS COMPANY OCTOBER 2009
32 PATCHING WELDING PIPELINE AT IKOT IYANG NIGERIAN GAS COMPANY OCTOBER 2009
33 ON-LINE LEAK REPAIR GAS PIPELINE AT OKADA NIGERIAN GAS COMPANY DECEMBER 2009
34 ON-LINE LEAK REPAIR ABA-AFAM GAS PIPELINE NIGERIAN GAS COMPANY JANUARY 2010
35 PATCH WELDING ON ALAKIRI-ELEME GAS PIPELINE NIGERIAN GAS COMPANY DECEMBER 2010
36 ON-LINE LEAK REPAIR LIA SPUR LINE LAGOS NIGERIAN GAS COMPANY DECEMBER 2010
37 ON-LINE LEAK REPAIR GAS PIPELINE AT AKUETE NIGERIAN GAS COMPANY FEBRUARY 2011
38 12" PATCH AT 2 WELD POINTS AT IMO-RIVER KM 17 NIGERIAN GAS COMPANY APRIL 2011
39 14" PATCH WELD AT ASCON LINE NIGERIAN GAS COMPANY MAY 2011
40 ON-LINE CRUDE LEAK REPAIR ON 24" PIPELINE SAPELE SEPLAT PETROLEUM JUNE 2011
41 ON-LINE LEAK REPAIR GAS PIPELINE AT SAPELE SEPLAT PETROLEUM JUNE 2011
42 12" PATCH WELD-RIVER AT KM 10 NIGERIAN GAS COMPANY AUGUST 2011
43 ON-LINE LEAK REPAIR OF 6NOS POINTS ON 24" PIPELINE SEPLAT PETROLEUM AUGUST 2011
44 ON-LINE LEAK REPAIR AND ANKOWRAP ON 36" GAS PIPELINE- LAGOS-BENIN NIGERIAN GAS COMPANY OCTOBER 2011
45 ON-LINE LEAK REPAIR GAS PIPELINE AT TINAPA OANDO JANUARY 2012
46 LEAK REPAIR ON FLANGE ON SCRUBBER AT EGBIN NIGERIAN GAS COMPANY FEBRUARY 2012
47 ON-LINE LEAK REPAIR GAS PIPELINE AT TINAPA OANDO FEBRUARY 2012
48 36" - LINE ONLINE LEAK REPAIR OGHARA NIGERIAN GAS COMPANY MAY 2010
49 36" - LINE ONLINE REINFORCEMENT, ONIPETESI, ONDO NIGERIAN GAS COMPANY FEBRUARY 2013
50 14" ON-LINE LEAK REINFORCEMENT, IBAFO NIGERIAN GAS COMPANY MAY 2013
51 CLAMPING OF LEAK-60 BAR EHGC PIPELINE AT UKANAFUN, AKWA-IBOM EHGC FEBRUARY 2014
52 14" PATCH WELD AFAM-OYIGBO PHC NIGERIAN GAS COMPANY FEBRUARY 2014
53 18" - ONLINE LEAK REPAIR, OANDO, CALABAR OANDO MARCH 2014
54 OWARZA 16" ONLINE LEAK REPAIR NIGERIAN GAS COMPANY MARCH 2014
55 24" ONLINE LEAK REPAIR AUCHI NIGERIAN GAS COMPANY JUNE 2014
56 24" ONLINE LEAK REPAIR UGBOKODO, DELTA STATE NIGERIAN GAS COMPANY AUGUST 2014
57 EMERGENCY 30" ONSHORE PIPELINE LEAK REPAIR AT ITOKI (KP 34+78) WEST AFRICAN GAS PIPELINE AUGUST 2014
58 Leak Inspection and Repair on the 18" X 62km Uquo Export Line ACCUGAS/SAVANNAH
59 24INCH Oron Pipeline Repair at KP35 ACCUGAS/SAVANNAH
60 EHGC Underwater P/L Inspection and Repair at Adiabo River Crossing ACCUGAS/SAVANNAH

LIST OF SECTIONAL REPLACEMENT AND PIPELINE CONSTRUCTION PROJECTS

S/N ACTIVITIES DESCRIPTION CLIENT
1 14", 16" X 1KM TABA/NGC
2 SECTIONAL REPAIR OF KP30"29 PIPELINE (UTOROGU-WGTP) NIGERIAN GAS COMPANY
3 SECTIONAL REPLACEMENT-SAPELE GAS PIPELINE NIGERIAN GAS COMPANY
4 SAPELE METERING STATION CATHODIC PROTECTION NDPHC/NGC
5 INTELLIGENT PIGGING OF 18" SAPELE GAS PIPELINE NDPHC/CMES
6 CONSTRUCTION OF 16" X 1KM PIPELINE AT SAPELE NDPHC/CMES
7 CATHODIC PROTECTION EVALUATION 34KM OBEN- SAPELE GAS PIPELINE NDPHC/CMES
8 COATING PROTECTION EVALUATION KM OBEN- SAPELE GAS PIPELINE NDPHC/CMES
9 CONSTRUCTION OF 18" X 1KM ADDAX FLOW STATION IZOMBE OILSERV/NDPHC
10 ENGINEERING PROCUREMENT AND CONSTRUCTION OF GAS PIPELINE OF 8" x 4.5KM, 2" X 3.15KM PIPELINE, SUPPLY OF 8NOS PRMS AND INSTALLATION NIGERIAN GAS COMPANY
11 CONSTRUCTION OF 4" X 717M BANANA ISLAND GELMAK
12 ENGINEERING PROCUREMENT INSTALLATION & CONSTRUCTION OF 4" GAS PIPELINE TO FENICE METAL INDUSTRIES SAGAMU NGC
13 INTEGRITY TESTING OF 24" X 1.3KM RIVER NIGER CROSSING AMAZON/AGIP
14 PIPELINE HYDROTESTING AND REPAIR OF 24" X 1.3KM KWALE – AKRI RIVER NIGER CROSSING AMAZON/AGIP
15 24 inch KM" KWALE - AKRI GAS PIPELINE AMAZON/AGIP
16 36" X 20KM PIPELINE CONSTRUCTION OF LEKKI GAS PIPELINE PROJECT ZAKHEM/DANGOTE
17 12" x 10km Pipeline Baleine Project Abidjan KUYO/ENI